Submitting a Pearl Rating Application
All relevant new PRS projects must achieve a minimum 1 Pearl rating to receive approval from the planning and permitting authorities. Government-funded PBRS and PVRS projects must achieve a minimum 2 Pearl rating.
Registration of projects for Pearl Ratings with DPM is not required at present. A formal registration process will be in place in the future.
The submission requirements for the design and construction stages of the Pearl Rating System (PRS) are outlined in each credit.
The Design Rating application is linked with the building permitting process at the relevant Municipalities and must be made at the end of the construction documentation stage. The Construction Rating application must be made on completion of construction.
Any building and villa project located within a proposed pearl rated community must demonstrate an integrated approach between the PCRS application and the PBRS/PVRS application(s). The PCRS application must be submitted and approved before NOPC letters can be issued for the individual project villas and/or buildings.
Confidentiality
There will be no public disclosure of information provided as part of the Submission Requirements. Information provided will remain confidential, except as required for identification of the project and its key participants for the purposes of providing Certification.
Estidama Correspondence
All credit related commitment/undertaking letters are to be included within the relevant credit folder of the Pearl Rating System submission. Hard copies of these letters are NOT required to be submitted.All correspondence submitted must be signed by the appointed PQP for the project or the company authorised signatory.
Any required Estidama PRS submission correspondence must be submitted to the related responsible entity in accordance with Information Bulletin 18 and addressed to the representatives below where applicable:
Department of Urban Planning and Municipalities (DPM) (post 21st February 2019)
H.E. Hamad Abdullah Al Mutawa
Executive Director
Operations Affairs Sector
Department of Urban Planning and Municipalities
6th Floor Al Mamoura Building
Abu Dhabi Municipality (ADM) (post 21st February 2019)
H.E. Eng. Khalfan Sultan Al Nuaimi
Executive Director
Town Planning Sector
Abu Dhabi City Municipality
Cover Letter Requirements
All Pearl Rating System (PRS) application cover letters must include the following summary table AND attach a signed copy of the Estidama Completeness Checklist (applicable to Design and Construction Rating submissions).
All fields highlighted in yellow must be UPDATED for resubmission:
Project Name |
|
Completeness Checklist Attached? (Yes/No) |
For Design Rating applications, the PQP must attach the signed Estidama Completeness Checklist to cover letter: CLICK HERE TO DOWNLOAD FOR DESIGN CLICK HERE TO DOWNLOAD FOR CONSTRUCTION Provide the scanned copy and the excel version of this checklist within the IDP-R1 credit folder. |
Plot Number |
Obtained from Municipal Affection Plan |
Sector |
Obtained from Municipal Affection Plan |
Municipality |
ADM/ AAM / DRM |
Municipality Project ID |
Where available |
Pearl Rating System |
e.g. PBRS, PCRS or PVRS |
Pearl Rating Stage |
Design or Construction |
Pearl Rating Targeted |
e.g. 1 Pearl, 2 Pearls etc. |
Submission Type |
e.g. First Submission or Re-submission #1, #2 etc. PLEASE UPDATE THIS FIELD UPON RESUBMISSION. For Re-submissions, please attach EITHER: 1. The latest issued DPM comment sheet with the completed PQP responses to DPM’s comments OR 2. The Notice of Incomplete Submission Email (for incomplete submissions) |
RE-R1 Compliance Pathway |
Prescriptive or Performance (N/A for PCRS) |
GFA (m2) |
GFA of the building/villa typology submitted. See definition below. |
Estidama Project ID |
- Applicable for re-submissions. - Click here for guidance on where to find the project ID. - For resubmissions, please attach the latest issued DPM review sheet completed with PQP responses to the cover letter. |
Urban Development ID |
If applicable |
Comments |
Where applicable, please: |
1. List any previously approved similar typologies with their corresponding Project ID numbers. |
|
2. Note if the project was previously deemed incomplete. |
|
Owner/Owner's Representative Contact Details (provide contact details of the person responsible for receiving all official correspondence for this project) |
|
Name |
|
Job Title |
|
Company |
|
Email Address |
GFA: The sum of the floor areas of the spaces within a building, including basements, mezzanines and intermediate floors, and penthouses with an internal height of 2.3m or greater. It is measured from the exterior faces of the exterior walls or from the centreline of walls separating buildings. It excludes covered walkways, porches, pipe trenches, exterior terraces or steps, chimneys, roof overhangs and similar features.
Please note all credit related commitment/undertaking letters are to be included within the relevant credit folder of the Pearl Rating System submission. The DPM does not require the hard copies of these letters to be submitted.
Design Rating Application
All applicable Community, Building and Villa projects must submit the Design Rating Application to DPM following the instructions below:
From 1 June 2011, all PRS submittals must be undertaken by a certified PQP in the applicable rating system.
Download the submittal template and the accompanied submittal guide for either a Community, Building or Villa project.
DPM's Estidama Pearl Rating System Review Process
Following submission of the Pearl Rating application to the DPM, the Estidama team will review the application and provide feedback and comments to both the project PQP and to the project owner. The flow chart below illustrates the review process for projects aiming for minimum 1 Pearl (privately funded) or minimum 2 Pearl (government funded) rating.
The DPM Estidama team is available throughout the review process to help project teams in obtaining rating approvals in no more than two submissions over a period of less than two months.
Assessment Protocol Flow Chart
Projects that have received a Pearl Design rating and are under construction are required to submit a Pearl Construction Rating application after construction is completed. At this point, the Pearl Design Rating will be superseded by the Construction Rating. The Construction Rating application follows the same process as the design one. Project teams can update the previously submitted templates including a concise description of the changes that occurred between obtaining the design rating and completion of construction. The instructions of the submission process are outlined above.
Currently, all Construction Rating applications must be submitted as described above in the Estidama Correspondence section.